Cadence finds 33% savings for Amapá plant-production

Cadence Minerals plc has identified savings of 33% for processing plant recommissioning and increased production at the Amapá iron ore project in northeast Brazil. REDESIGN A capital expenditure optimisation programme, conducted at pre-feasibility level, showed US$63.2 million savings associated with the plant. This sees costs fall from $191.7m to $128.5m. Forecast increased production is approximately […]

Equipment & Logistics Metals & Minerals News

$210m beneficiation plant contract for Yangibana

The Yangibana rare earths project in Western Australia has progressed with a $210 million contract, in line with staged development, for a beneficiation plant and associated infrastructure. SCHEDULE Cadence Minerals plc said that the operator Hastings Technology Metals had signed the engineering, procurement and construction (EPC) agreement with GR Engineering Services Ltd. The contract includes […]