West Cumbria Mining Ltd (WCM) said that the rolled-up hearing relating to challenges against the Government’s planning approval for a deep coal mine has been postponed.

RESCHEDULED

The company added it continued to progress towards the pre-start work required, including design, planning, equipment procurement and associated desk-based work.

The hearing, set for 24 to 26 October 2023, will be rescheduled to a later date after judgement on an unrelated case objecting to approval for UK Oil & Gas onshore oil operations at Horse Hill in Surrey.

“The hearing will now be re-scheduled to be heard after judgement has been handed down by the Supreme Court on another case (Finch),” added WCM in its statement.