Helium One Global Ltd has appointed a 24-hour drill crew and completed 90% of setting up the rig on Tai-C well for phase II drilling at Rukwa in Tanzania.
CONTRACTS
The remaining long lead items are on schedule to arrive during the second week of September with drilling on course to start during the second half of the same month.
Helium One has also appointed third-party services personnel, an operator supervisory team and signed a contract with Container Concepts Ltd which is currently mobilising to site.
“This is an incredibly exciting time for the company as we approach the spud of Tai-C in the second half of September,” said chief executive officer Lorna Blaisse.
“The team has worked very hard to get us to this point and we look forward to the last few items required to fall into place.”