Helium One Global Ltd’s partner has spud the Jackson-29 SWNW 3054 development well at the Galactica helium project in Las Animas County, Colorado, USA.

READINGS
Operator Blue Star Helium is currently preparing to drill intermediate hole section.
“The shallow conductor section has been set and blowout preventers are being installed and tested, and the next phase will be to drill through the intermediate hole section,” said Helium One.
“After casing at the base of the intermediate section, the well will target the Lyons Sandstone formation, with target depth (TD) planned within the Upper Lyons formation gas reservoir.
“When TD is reached, wireline logging will then be conducted, followed by flow and pressure readings at the wellhead.
“This data will be used to estimate the production potential of the well based on the production model.”
Once completed, the JV will tie in Jackson-29 to production facilities.
The Galactica project is part of the broader Galactica/Pegasus development, discovered by Blue Star in 2022.