Cora Gold Ltd said it was on course to complete the definitive feasibility study for its Sanankoro gold project in Southern Mali.
OPERATIONS
The company has completed on schedule all hydrogeological and geotechnical drilling, associated pump testing and geotechnical test pits.
All field-based sampling work is now complete and final samples are being dispatched to the relevant laboratories
Metallurgical test work continues is ongoing while all major procurement packages have been sent to suppliers for costing.
Cora has also finalised site layout, including locations of the plant, tailings storage facility and camp accommodation.
The environmental and social impact assessment (ESIA) remains on target for completion during H1 2022 while the DFS is due to completed by end of H1 2022.