Angus Energy plc said it maintained its target date of 1 June for first gas at Saltfleetby in East Lincolnshire.
OPERATIONS
The operator added it was progressing with the project’s installation and commissioning schedule.
Skid/Unit | Basc Fabrication Status | Blasting, Painting Assembly, Testing, Certification etc | Target Delivery Date |
Electrical Room | 100% complete | Completed | Completed |
Separator Vessel | 100% complete | Completed | Completed |
Passive Dehydration | 100% complete | Completed | Completed |
1st compression | 100% complete | Completed | 27 April |
Gas Engine Generator | 100% complete | 90% complete | 29 April |
Export Filters/Diverters | 100% complete | Re-assembly | 3 May |
Condensate Stabilisation Skid | 100% complete | Reassembly | 4 May |
Joule Thomson Skid | 100% complete | Re-assembly | 5 May-10 May |